M&M Data Migration arc42 section 10
Quality Requirements
Not elaborated in the original. The section exists there under the heading Quality scenarios and is marked “omitted in this example”.
The two quality goals that actually drove this architecture are stated in section 1.2: migrate ~20 million person and account records within 24 hours, and do it in an audit-proof and legally sound way. Almost every decision in section 9 traces back to one of those two.